Retainage is a percentage of each progress payment — commonly ten per cent — that the owner withholds until the job is complete. It is revenue you have earned and cannot collect, and it is the reason a construction business can be profitable on paper and short of cash in the same month.
Retainage as its own receivable
Held in the general receivables balance, retainage distorts ageing, distorts collections, and makes the cash forecast wrong. In its own account it answers the question the business actually has: how much have we earned that is being held, on which jobs, and when is it releasable.
The same applies on the payable side. Retainage withheld from subcontractors is an obligation with a release condition, and it should be as visible to you as yours is to the owner.
Progress billing
The G702 is the application and certificate; the G703 is the continuation sheet behind it, line by line against the schedule of values. Each application restates everything to date: scheduled value, previously billed, billed this period, stored materials, retainage, balance to finish.
Built from the job ledger, that document is a report. Built by hand, it is a monthly reconstruction that is wrong often enough to delay payment — which in this industry is the expensive failure, because the payment funds the next month of work.
Lien waivers
| Control | Enforced how | Risk if it is not |
|---|---|---|
| Conditional waiver before payment | System hold on the payment run | Paying a sub whose own suppliers can still lien the property. |
| Unconditional waiver after clearing | Document logged against the payment | No evidence the claim was released. |
| Insurance certificate currency | Expiry date checked at payment | An uninsured sub on site, discovered after an incident. |
Every one of these is enforceable by the system at the moment of payment. Enforced by a person with a checklist, they hold until the week the schedule is tight.
Percentage-of-completion
Revenue is recognised as cost incurred divided by estimated total cost. The estimate is a judgement made by people who are also responsible for the job's result, and revising it upward restates revenue already recognised.
Two disciplines keep this honest: estimates are updated on a schedule and not when convenient, and the revision history is retained. A cost-to-complete that only moves at quarter end is a number being managed, not measured.
Job cost, live
Committed cost — issued purchase orders and subcontracts — belongs in the job view alongside actuals. A project manager looking only at posted costs sees a position that is weeks stale and consistently better than reality.